Finishing and Dispatch Department Building Update

21 April 2017

TMJ's Finishing and Dispatch Department new building is in full swing and we are exciting to start using it! We have completed 100% of the external cladding and 100% of the brickwork, 3 gas tanks have been installed along with a lorry wash area.

We are currently in process of installing a staircase to the outside of the building for a fire escape and the spray booths are expected to arrive in May 2017.

The new development will be operation early June 2017.